Road Closures and Site visitors Impacts

CORPUS CHRISTI, TX – Road closures alongside main Metropolis streets impacting motorists and pedestrians are listed under. These closures could also be attributable to development, particular occasion exercise, or upkeep. All closures are topic to vary attributable to climate, emergency work, or different circumstances.
Work zone security is a precedence. Motorists are suggested to decelerate, observe posted pace limits, concentrate, be careful for employees, obey indicators and flaggers, and permit further journey time for delays.
CITY STREET RECONSTRUCTION OR MAINTENANCE PROJECTS
Brawner Parkway – Kostoryz Street to Carroll Lane (Bond 2018)
Throughout Part 2 of Brawner Parkway development, visitors north and south of the median is decreased to one-way within the westbound course from Carroll Lane to Kostoryz Street.
Fairview Drive – Up River Street to Kenwood Drive (RSRP)
Fairview Drive is closed for road reconstruction between Up River Street and Kenwood Drive. Residents alongside Fairview Drive will likely be supplied with native entry. Development is anticipated to final a number of months.
Junior Beck Street – Bear Lane to Outdated Brownsville Street (Bond 2018)
Throughout this Part 2 of the venture, Junior Beck Street will likely be briefly transformed to one-way visitors within the southbound course from Bear Lane in direction of Outdated Brownsville Street. The Company Drive intersection at Junior Beck will likely be briefly closed for this part. Residents will proceed to have native entry from South Padre Island Drive (SPID) Entry Street. Wayfinding and detour signage will likely be in place to information motorists to their locations. The momentary one-way and intersection closure is anticipated to final a number of months.
Leopard Road – Palm Drive to Nueces Bay Boulevard (Bond 2018)
Leopard Road is decreased to 1 lane, in every course, alongside the eastbound lanes (south facet) of Leopard Road between Nueces Bay Boulevard and Battlin’ Buc Boulevard. The intersection at Leopard Road and Nueces Bay Boulevard is open to visitors. Extra momentary intersection closures will likely be applied alongside the south facet of Leopard Road as development progresses.
Lengthy Meadow Drive – Saratoga Boulevard to St. Andrews Drive (Bond 2018)
Site visitors on Lengthy Meadow Drive is restricted to one-way solely within the northbound course from Saratoga Boulevard to St. Andrews Drive. Southbound visitors will likely be detoured to Wooldridge Street to entry Everhart Street or Staples Road. The one-way detour is anticipated to final for the venture’s period, and development is anticipated to final six months.
Park Street 22 Bridge and Channel – Whitecap Boulevard to Commodores Drive (SH 361)
Park Street 22 is closed for development on the south facet (eastbound lanes) between Compass Road and Cruiser Road. Motorists touring eastbound (south facet) alongside Park Street 22 are shifted to the westbound lanes (north facet) between Compass Road and Cruiser Road. Journey lanes in every course are decreased to 1 between Compass Road and Cruiser Road.
Staples Road – Baldwin Boulevard to Kostoryz Street (Bond 2018)
Development on Staples Road is transferring into the following part, the place visitors will shift to the east facet onto the newly constructed roadway. Site visitors will proceed to journey in a single lane in every course. The middle-turn lane will proceed to be closed throughout this part of development.
South Staples Road – Saratoga Boulevard to Williams (CSIP)
The contractor is performing upkeep on South Staples Road from Saratoga Boulevard to Williams Drive as a part of the Metropolis’s Concrete Streets Enchancment Mission.
Development will happen between the hours of seven:30 a.m. to 4:30 p.m., Monday by way of Friday.
The contractor will conduct each day single-lane closures alongside South Staples Road, starting on the Williams Drive intersection, and work southward in direction of Saratoga Boulevard. Intersections alongside the development path might expertise each day short-term closures or restrictions. Two-way visitors will stay open for motorists all through development.
Development period for this venture is anticipated to final two months, climate allowing.
Swantner Drive – Indiana Avenue to Texan Path (Bond 2018)
Swantner Drive is closed to via visitors between Ralston Road and Deforrest Road. Swantner Drive from Vaky Road to Glazebrook Road can also be closed to via visitors. Chamberlain Road and McClendon Road are open to native visitors. McCall Road will stay open from Reid Drive to Swantner Drive to permit entry to the Lindale Senior Middle.
Reid Drive, Glazebrook Road, and Swantner Drive from Glazebrook Road to Texan Path are open.
Wooldridge Street – Everhart Street to Cascade Drive (Bond 2018)
Contractors for the Metropolis are reconstructing Wooldridge Street between Everhart Street and Cascade Drive as a part of the Metropolis’s 2018 Bond Package deal. A brief full road closure of Wooldridge Street, between Everhart Street and Fenway Drive, will likely be in place. Motorists will keep native entry as much as the closure, and detour indicators will likely be in place to information visitors across the momentary closure. Motorists utilizing Wooldridge Street as a part of their each day commute are suggested to hunt alternate routes on Holly Street and Saratoga Boulevard by way of Everhart Street or Staples Road.
CITY PERMITTED CLOSURES
Ayers Steet – Horne Street to Gollihar Street
The contractor for AEP Texas is performing upkeep work on their services alongside Ayers Road from Horne Street to Gollihar Street. The contractor will implement numerous lane closures alongside this part of Ayers Road. Work at this location is anticipated to final one month.
Brett Road – Weber Street to Byron Road
A communication contractor is engaged on eradicating a communication pole inside the suitable of means. The contractor will implement momentary sidewalks and lane closures each day to facilitate their work zone. The contractor will keep residential, faculty, and enterprise entry always.
Motorists ought to use warning whereas driving by way of the work zone. Development is anticipated to final a number of days.
Caldwell Road – Mexico Road to Brownlee Boulevard (Guerra Underground)
The subcontractor for Flat Iron Dragados is putting in a brand new wastewater line between Mexico Road and Brownlee Boulevard as a part of the New Harbor Bridge Utility Relocation Mission. Development is progressing and is now in its closing part. A brief road closure of Caldwell Road between Mexico Road and Brownlee Boulevard will likely be in place for the ultimate part. A brief intersection closure of Caldwell Road and Mexico Road will likely be in place as development progresses to the west. Detour indicators will likely be in place to direct visitors across the momentary road closure. Residents will all the time have entry throughout development. Development is anticipated to final a number of months.
Carancahua Road – Agnes Road to Coopers Alley
The contractor for Corpus Christi Water Division is making pavement repairs on Carancahua Steet. The contractors will implement momentary lane closures alongside Carancahua Road between Agnes Road and Coopers Alley. Development is anticipated to final a number of weeks.
Castenon Road – Trojan Drive to Juarez Road
A communication contractor is engaged on eradicating a communication pole inside the suitable of means. The contractor will implement momentary sidewalks and lane closures each day to facilitate their work zone. Contractors will keep residential, faculty, and enterprise entry.
Motorists ought to use warning whereas driving by way of the work zone. Development is anticipated to final a number of days.
Cole Road – Santa Fe Road to Third Road
A communication contractor is engaged on eradicating a communication pole inside the suitable of means. The contractor will implement momentary sidewalks and lane closures each day to facilitate their work zone. Contractors will keep residential, faculty, and enterprise entry.
Motorists ought to use warning whereas driving by way of the work zone. Development is anticipated to final a number of days.
Cuiper Road – Carlton Road to Dinn Road
The contractor for Corpus Christi Water Division is repairing a wastewater line on Cuiper Road and implementing momentary road closures between Carlton Road and Dinn Road. Cuiper Road will briefly near all visitors between Carlton Road and Dinn Road. Motorists will proceed to have native entry as much as the closure. A detour will likely be in place to information visitors across the momentary closure. Development is anticipated to final a number of weeks.
Crescent Drive – McArdle Road to Winston Road
A communication contractor is engaged on eradicating a communication pole inside the suitable of means. The contractor will implement momentary sidewalks and lane closures each day to facilitate their work zone. The contractor will keep residential, faculty, and enterprise entry.
Motorists ought to use warning whereas driving by way of the work zone. Development is anticipated to final a number of days.
Deepwood Circle – South Padre Island Drive Entry Street to Lifeless Finish
A communication contractor is engaged on eradicating a communication pole inside the suitable of means. The contractor will implement momentary sidewalks and lane closures each day to facilitate their work zone. The contractor will keep residential, faculty, and enterprise entry.
Motorists ought to use warning whereas driving by way of the work zone. Development is anticipated to final a number of days.
Dillon Lane – Gollihar Street to South Port Avenue
A communication contractor is engaged on eradicating a communication pole inside the suitable of means. The contractor will implement momentary sidewalks and lane closures each day to facilitate their work zone. Contractors will keep residential, faculty, and enterprise entry.
Motorists ought to use warning whereas driving by way of the work zone. Development is anticipated to final a number of days.
Everhart Street – South Padre Island Drive to South Alameda Road
Gaines Road – Robert Road to Airline Street
The contractor for the Corpus Christi Water Division is repairing a wastewater line on Gaines Road and implementing momentary road closure between Robert Drive and Airline Street. Residential and enterprise entry will likely be maintained always throughout development. A detour will likely be in place to information visitors across the momentary closure. Development is anticipated to final a number of weeks.
Greely Drive – Belmeade Drive to Evergreen Drive
The contractor for personal growth is establishing a waterline throughout Greely Drive and has applied momentary road closures between Belmeade Drive and Evergreen Drive. Greely Drive will likely be briefly closed to all visitors between Belmeade Drive and Evergreen Drive. Motorists will keep native entry as much as the closure, and a detour will likely be in place to information visitors across the momentary closure. Development is anticipated to final a number of weeks.
Inexperienced Move Drive – Surrounding Neighborhood Streets
A communication contractor is engaged on upgrading cable tv strains and will likely be putting in services within the Inexperienced Move Drive neighborhood. The contractor will implement numerous momentary sidewalks and lane closures to facilitate their work zone. Residential entry will likely be maintained always.
Motorists ought to use warning whereas driving by way of the work zone. Development is anticipated to final a number of months.
Corridor Avenue – Lantana Road to Benys Street
A contractor for Corpus Christi Impartial Faculty District is performing development actions for the brand new Gibson Elementary Faculty alongside Corridor Avenue proper of means. The contractor will implement each day momentary lane closures alongside the college’s property at numerous occasions throughout development. Residential entry will likely be maintained always.
Motorists ought to use warning whereas driving by way of the work zone. Development is anticipated to final a number of months.
Key West Drive – Weber Street to Panama Drive
A communication contractor is engaged on eradicating a communication pole inside the suitable of means. The contractor will implement momentary sidewalks and lane closures each day to facilitate their work zone. Contractors will keep residential, faculty, and enterprise entry.
Motorists ought to use warning whereas driving by way of the work zone. Development is anticipated to final a number of days.
Lipes Boulevard – Giants Drive to Airline Street
A contractor for personal growth is making a waterline connection to an present waterline on Lipes Boulevard. Contractors will implement a each day lane closure lowering the road to 1 journey lane. Flaggers will likely be on each ends of the closure, helping motorists by way of the one journey lane. Motorists are urged to make use of warning as they navigate by way of the work zone. Each day lane closures are anticipated to final a few weeks.
McArdle Street – Franklin Drive to Gabriel Drive
A communication contractor is engaged on eradicating a communication pole inside the suitable of means. The contractor will implement momentary sidewalks and lane closures each day to facilitate their work zone. Contractors will keep residential, faculty, and enterprise entry.
Motorists ought to use warning whereas driving by way of the work zone. Development is anticipated to final a number of days.
Port Avenue – Horne Street to Baldwin Boulevard (Clark Pipeline)
The contractor is changing a 16-inch water essential alongside South Port Avenue from Horne Street to Baldwin Boulevard. Development has progressed into the following part. Nonetheless, Southbound Port Avenue will stay decreased to 1 lane between Baldwin Boulevard and Tarlton Road, using the middle flip lane because the journey lane. Northbound Port Avenue journey lanes is not going to be affected. In distinction, different lane closures alongside the venture limits might happen for lateral waterline installations. Development at this location is estimated to final a number of months.
Prescott Road – at Trojan Drive Intersection
A communication contractor is engaged on eradicating a communication pole inside the suitable of means. The contractor will implement momentary sidewalks and lane closures each day to facilitate their work zone. Contractors will keep residential, faculty, and enterprise entry.
Motorists ought to use warning whereas driving by way of the work zone. Development is anticipated to final a number of days.
River Run Street – Surrounding Neighborhood Streets
The contractor will implement numerous momentary sidewalks and momentary lane closures to facilitate their work zone Residential entry will likely be maintained always.
Motorists ought to use warning whereas driving by way of the work zone. Development is anticipated to final a number of months.
Rossiter Road – South Alameda Road to Santa Fe Road
The contractor for Corpus Christi Water Division is repairing a wastewater line on Rossiter Road and implementing momentary road closure between South Alameda Road and Santa Fe Road. Rossiter Road will likely be briefly closed to all visitors between South Alameda Road and Santa Fe Road. Motorists will keep native entry as much as the closure, and a detour will likely be in place to information visitors across the momentary closure. Development is anticipated to final a number of weeks.
Santa Fe Road – Primrose Drive to Rossiter Road
The contractor for the Corpus Christi Water Division is repairing a wastewater line that runs throughout Santa Fe Road. To make repairs, contractors will carry out each day lane closures on Santa Fe Road between Primrose Drive and Rossiter Road. Development is anticipated to final 30 days.
Sydney Road – Boomerang Drive to Las Bahias Drive
A communication contractor is engaged on eradicating a communication pole inside the suitable of means. The contractor will implement momentary sidewalks and lane closures each day to facilitate their work zone. The contractor will keep residential, faculty, and enterprise entry always.
Motorists ought to use warning whereas driving by way of the work zone. Development is anticipated to final a number of days.
Sixth Road – Ayers Road to Booty Road
A communication contractor is engaged on eradicating a communication pole inside the suitable of means. The contractor will implement momentary sidewalks and lane closures each day to facilitate their work zone. Contractors will keep residential, faculty, and enterprise entry.
Motorists ought to use warning whereas driving by way of the work zone. Development is anticipated to final a number of days.
Wilkinson Drive – Tiger Lane to Bentwood Lane
A communication contractor is engaged on eradicating a communication pole inside the suitable of means. The contractor will implement momentary sidewalks and lane closures each day to facilitate their work zone. The contractor will keep residential, faculty, and enterprise entry.
Motorists ought to use warning whereas driving by way of the work zone. Development is anticipated to final a number of days.
Wooden River Drive – Surrounding Neighborhood Streets
A communication contractor is engaged on a fiber construct venture and putting in services within the Wooden River Drive Neighborhood.
The contractor will implement numerous momentary sidewalks and lane closures to facilitate their work zone. Residential entry will likely be maintained always.
Motorists ought to use warning whereas driving by way of the work zone. Development is anticipated to final a number of months.
Yorktown Boulevard – Rodd Area Street to Geiger Drive
A contractor for personal growth is establishing driveways for brand spanking new retail growth property. The contractor will implement momentary sidewalks and lane closures alongside the eastbound journey lanes to carry out driveway development. Motorists ought to use warning whereas driving by way of the work zone. Development is anticipated to final a number of days.
SPECIAL EVENT PERMITTED CLOSURES
Hearts and Minds 5K Run
Corpus Christi Schooling Basis could have its annual Hearts and Minds 5K Run to assist fund applications for CCISD college students. This 12 months’s occasion will begin and finish at Texas A&M College-Corpus Christi Campus. The route will run out of the campus onto Ocean Drive in direction of Naval Air Station North Gate and again to the campus.
Campus entry will likely be maintained always throughout the occasion. Momentary lane closures for the occasion are anticipated to final by way of the morning.